MIS LOG IN

RMGRR106

Summary

Title Clarifies E-mail Process for Safety-Net and Emergency Reconnect Requests and Adds a Spanish Version of the New Occupant Statement
Next Group
Next Step
Status Approved on 01/05/2012
Effective Dates
02/01/2012

Action

Date Gov Body Action Taken Next Steps
01/05/2012 TAC Approved
12/14/2011 RMS Recommended for Approval TAC for consideration.
11/16/2011 RMS Recommended for Approval RMS for Impact Analysis review.

Voting Record

Date Gov Body Motion Result
01/05/2012 TAC To approve RMGRR106 as recommended by RMS in the 12/14/11 RMS Report as revised by TAC. Passed
12/14/2011 RMS To endorse and forward the 11/16/11 RMS Report as amended by the 12/6/11 Oncor comments and as revised by RMS and the Impact Analysis for RMGRR106 to TAC. Passed
11/16/2011 RMS To recommend approval of RMGRR106 as amended by the 11/14/11 CenterPoint Energy comments and as revised by RMS. Passed

Background

Status: Approved
Date Posted: Oct 31, 2011
Sponsor: Karla Franco on behalf of CenterPoint Energy
Urgent: No
Sections: 7.4.1.4, 7.6.5.1, 7.6.5.6, 7.16.4.3.2, 7.17.3.3.2, 9J3
Description: This Retail Market Guide Revision Request (RMGRR) clarifies the e-mail process used for submitting safety-net and emergency reconnect requests to Transmission and/or Distribution Service Providers (TDSPs) and also updates the CenterPoint Energy (CNP) e-mail address used for submitting those requests. In addition, this RMGRR also introduces a Spanish version of the New Occupant Statement form.
Reason: These changes will eliminate confusion that Retail Electric Providers (REPs) may have when submitting standard and priority safety-net requests as well as emergency reconnect requests to TDSPs. New Appendix J3, Declaración De Nuevo Ocupante (New Occupant Statement -- Spanish), provides Competitive Retailers (CRs) the ability to have both English and Spanish versions available when taking move in applications from retail Customers.

Key Documents