MIS LOG IN

RMGRR115

Summary

Title Manual Work-Around Processes to be Utilized During Extended Retail Outages
Next Group
Next Step
Status Approved on 09/05/2013
Effective Dates
10/01/2013

Action

Date Gov Body Action Taken Next Steps
09/05/2013 TAC Approved
08/21/2013 RMS Recommended for Approval TAC for consideration.
07/17/2013 RMS Recommended for Approval RMS for Impact Analysis for review.
03/20/2013 RMS Referred Retail Lessons Learned Task Force for language consideration.

Voting Record

Date Gov Body Motion Result
09/05/2013 TAC To approve RMGRR115 as recommended by RMS in the 8/21/13 RMS Report Passed
08/21/2013 RMS To endorse and forward the 7/17/13 RMS Report and Impact Analysis for RMGRR115 to TAC. Passed
07/17/2013 RMS To recommend approval of RMGRR115 as amended by the7/16/13 Oncor comments and as revised by RMS. Passed
03/20/2013 RMS To refer RMGRR115 to the Retail Lessons Learned Task Force. Passed

Background

Status: Approved
Date Posted: Feb 28, 2013
Sponsor: Kyle Patrick on behalf of the Retail Lessons Learned Task Force
Urgent: No
Sections: 7.4.1, 7.4.1.1, 7.4.1.3, 7.4.1.4, 7.16.4.3.4, 7.17.3.3.4
Description: This Retail Market Guide Revision Request (RMGRR) provides guidelines for the use of manual workarounds during an extended outage that affects retail market processing of Customer move ins, move outs and switch hold removals.
Reason: This RMGRR addresses issues associated with the 12/3/13 ERCOT outage as identified by the Retail Lessons Learned Task Force.

Key Documents