MIS LOG IN

RRGRR008

Summary

Title Alignment with NPRR705, Provides Consistency for References to the End Date of the Generation Interconnection Process
Next Group
Next Step
Status Approved on 12/16/2015
Effective Dates
01/01/2016

Action

Date Gov Body Action Taken Next Steps
12/16/2015 TAC Approved
10/29/2015 TAC Deferred/Tabled Revision Request Consideration
10/08/2015 ROS Recommended for Approval Revision Request Consideration
09/03/2015 ROS Deferred/Tabled Revision Request Consideration
08/18/2015 RDWG Recommended for Approval Revision Request Consideration
07/14/2015 RDWG Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
12/16/2015 TAC To approve RRGRR008 as recommended by ROS in the 10/8/15 ROS Report. Passed
10/29/2015 TAC To table RRGRR008. Passed
10/08/2015 ROS To recommend approval of RRGRR008 as recommended by RDWG in the 8/18/15 RDWG Report. Passed
09/03/2015 ROS To table RRGRR008. Passed
08/18/2015 RDWG To endorse and forward to ROS the 7/14/15 RDWG Report and Impact Analysis for RRGRR008. Passed
07/14/2015 RDWG To recommend approval of RRGRR008 as revised by RDWG. Passed

Background

Status: Approved
Date Posted: May 20, 2015
Sponsor: ERCOT
Urgent: No
Sections: 2
Description: In the Resource Interconnection Handbook, the term “commercial operations” has a different meaning to Resource Entities and financial institutions involved in construction and financing of Generation Resources than it does in the context of performance testing by ERCOT for new Generation Resources. This Recourse Registration Glossary Revision Request (RRGRR) aligns the Resource Registration Glossary with NPRR705 by replacing various terms used to refer to the date on which Generation Resources complete the Resource interconnection process with the proposed defined terms “Commercial Operations Date” and “Resource Commissioning Date” to provide consistency for references to the end of the generation interconnection process.
Reason: Administrative

Key Documents