to approve RRGRR029 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307, Review of Rules Adopted by the Independent Organization in Calendar Year 2021.
to table RRGRR029 and refer the issue to the Operations Working Group (OWG) and Planning Working Group (PLWG)
Passed
Background
Status:
Approved
Date Posted:
May 19, 2021
Sponsor:
ERCOT
Urgent:
No
Sections:
Section 2, Resource Registration Glossary – Unit Information and Section 2, Resource Registration Glossary – Parameters
Description:
This Resource Registration Glossary Revision Request (RRGRR) allows an Interconnecting Entity proposing a Settlement Only Generator (SOG) to designate that SOG as part of a Self-Limiting Facility for the purposes of the Generator Interconnection or Modification (GIM) process and provide that information using the same fields that RRGRR023, Related to NPRR1002, BESTF-5 Energy Storage Resource Single Model Registration and Charging Restrictions in Emergency Conditions, introduced for that purpose. The RRGRR is consistent with NPRR1077, which broadens the Self-Limiting Facility concept in the Protocols to allow SOGs to be designated as part of a Self-Limiting Facility.
Reason:
Addresses current operational issues; Market efficiencies and enhancements