RRGRR032

Summary

Title Related to NPRR1132, Communicate Operating Limitations during Cold and Hot Weather Conditions
Next Group
Next Step
Status Approved on 01/26/2023
Effective Dates
02/01/2023

Action

Date Gov Body Action Taken Next Steps
01/26/2023 PUCT Approved
12/20/2022 BOARD Recommended for Approval Revision Request Consideration
12/05/2022 TAC Recommended for Approval Revision Request Consideration
11/07/2022 ROS Recommended for Approval Revision Request Consideration
09/29/2022 ROS Recommended for Approval Impact Analysis Consideration
06/02/2022 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
01/26/2023 PUCT to approve RRGRR032 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization Passed
12/20/2022 BOARD to recommend approval of RRGRR032 as recommended by TAC in the 12/5/22 TAC Report Passed
12/05/2022 TAC to recommend approval of RRGRR032 as recommended by ROS in the 11/7/22 ROS Report as amended by the 12/2/22 ERCOT comments Passed
11/07/2022 ROS to recommend approval of RRGRR032 as amended by the 9/9/22 ERCOT comments as revised by ROS Passed
09/29/2022 ROS to recommend approval of RRGRR032 as amended by the 9/9/22 ERCOT comments as revised by ROS Passed
06/02/2022 ROS to table RRGRR032 for further review by the Operations Working Group (OWG) Passed

Background

Status: Approved
Date Posted: Apr 26, 2022
Sponsor: ERCOT
Urgent: No
Sections: Section 2 - Unit Information
Description: This Resource Registration Glossary Revision Request (RRGRR) adds data required to be shared with the ERCOT as the Reliability Coordinator, Balancing Authority, and Transmission Operator for use in considering cold weather limitations in its Operational Planning Analysis, Real-Time monitoring, Real-Time assessments, and other analysis functions. ERCOT is also requiring this information for hot weather limitations. Finally, ERCOT is requiring Distributed Generation Resources (DGRs) and Distributed Energy Storage Resources (DESRs) to provide this information. ERCOT is also listing alternate fuel supply information to aid in the same analysis described above.
Reason: Regulatory requirements