RRGRR033
Summary
Title
Related to NPRR1164, Black Start and Isochronous Control Capable Identification
Next Group
Next Step
Status
Approved on 10/12/2023
Voting Record
Date
Gov Body
Motion
Result
10/12/2023
PUCT
to approve RRGRR033 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization
Passed
08/31/2023
BOARD
to recommend approval of RRGRR033 as recommended by TAC in the 8/22/23 TAC Report
Passed
08/22/2023
TAC
to recommend approval of RRGRR033 as recommended by ROS in the 8/3/23 ROS Report
Passed
08/03/2023
ROS
to endorse and forward to TAC the 7/6/23 ROS Report and 2/21/23 Impact Analysis for RRGRR033
Passed
07/06/2023
ROS
to recommend approval of RRGRR033 as submitted
Passed
04/06/2023
ROS
to table RRGRR033 and refer the issue to the Network Data Support Working Group (NDSWG) and the System Protection Working Group (SPWG)
Passed
Background
Status:
Approved
Date Posted:
Feb 21, 2023
Sponsor:
ERCOT
Urgent:
No
Sections:
Section 2 – GENERAL_SITE_ESIID_Information – General and Site Information, and Section 2 – Breaker Switch Data (as applicable)
Description:
This Resource Registration Glossary Revision Request (RRGRR) adds data to the Resource Registration Glossary pursuant to NPRR1164.
Reason:
Other