Summary
Title | Posting Results of Real-Time Data in a Display Format |
---|---|
Next Group | |
Next Step | |
Status | Approved on 02/11/2014 |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
02/11/2014 | BOARD | Approved | |
01/28/2014 | TAC | Recommended for Approval | ERCOT Board for consideration. |
01/16/2014 | PRS | Recommended for Approval | TAC for consideration. |
12/19/2013 | PRS | Deferred/Tabled | PRS for consideration. |
11/21/2013 | PRS | Recommended for Approval | PRS for Impact Analysis review. |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
02/11/2014 | BOARD | To approve SCR775 as recommended by TAC in the 1/28/14 TAC Report. | Passed |
01/28/2014 | TAC | To recommend approval of SCR775 as recommended by PRS in the 1/16/14 PRS Report. | Passed |
01/16/2014 | PRS | To to endorse and forward the 12/19/13 PRS Report as revised by PRS and the Impact Analysis for SCR775 to TAC with a recommended priority of 2014 and rank of 1100. | Passed |
12/19/2013 | PRS | To table SCR775 | Passed |
11/21/2013 | PRS | To recommend approval of SCR775 as submitted. | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Oct 3, 2013 |
Sponsor: | ERCOT Steel Companies |
Urgent: | No |
Sections: | |
Description: | This System Change Request (SCR) adds two new displays to the Day-Ahead and Real-Time data displays section under the Market Information tab on the ERCOT Market Information System (MIS). RTD Load Zone Forecasted Prices RTD Hub Forecasted Prices Each pricing display would automatically update with new revised prices on each execution of Real-Time data and delete the oldest data as shown in the examples. As an option, ERCOT would also provide the ability of a MIS user to specify a price threshold selected by the user that would cause the displayed prices that exceed this threshold to be highlighted in a different background color. |
Reason: | Many large industrial loads purchase at least a portion of their power based on the Real-Time Locational Marginal Price (LMP) for a Load Zone or have arrangements with their Load Serving Entity (LSE) to interrupt when prices reach a certain threshold established by contract. Real-Time data provides a source for forecasted prices, but currently is only in a Comma Separated Value (CSV) or Hypertext Markup Language (HTML) format. These files contain all the LMPs from Real-Time data for all Resource Nodes, Hubs, and Load Zones when a particular load is only interested in the prices at a specific Load Zone or Hub Real-time data output files show LMPs for all Resource Nodes, Hubs, and Load Zones in a time sequential order making it difficult to sort out the changes in price projections for an individual Load Zone. To understand potential price excursions, a history of forecasted prices for an individual location is needed Low prices can be as important as high prices Loads need to be able to access MIS directly from ERCOT using simple off-the shelf products Windows IE, Firefox, etc. |
Key Documents
Oct 3, 2013 - doc - 543.5 KB
Nov 14, 2013 - doc - 39.5 KB
Nov 25, 2013 - doc - 548 KB
Dec 18, 2013 - doc - 55.5 KB
Dec 18, 2013 - doc - 520.5 KB
Dec 23, 2013 - doc - 549 KB
Jan 15, 2014 - doc - 66 KB
Jan 20, 2014 - doc - 554 KB
Jan 20, 2014 - xls - 102 KB
Jan 29, 2014 - doc - 557 KB
Feb 14, 2014 - doc - 558 KB