SCR795
Summary
Title | Addition of Intra-Hour Wind Forecast to GTBD Calculation |
---|---|
Next Group | |
Next Step | |
Status | Approved on 04/10/2018 |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
04/10/2018 | BOARD | Approved | |
03/22/2018 | TAC | Recommended for Approval | Revision Request Consideration |
03/08/2018 | PRS | Recommended for Approval | Revision Request Consideration |
02/08/2018 | PRS | Recommended for Approval | Impact Analysis Consideration |
12/14/2017 | PRS | Deferred/Tabled | Language Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
04/10/2018 | BOARD | approved SCR795 as recommended by TAC in the 3/22/18 TAC Report | Passed |
03/22/2018 | TAC | to recommend approval of SCR795 as recommended by PRS in the 3/8/18 PRS Report | Passed |
03/08/2018 | PRS | to endorse and forward to TAC the 2/8/18 PRS Report and the Impact Analysis for SCR795 with a recommended priority of 2018 and rank of 2200 | Passed |
02/08/2018 | PRS | to recommend approval of SCR795 as submitted | Passed |
12/14/2017 | PRS | to table SCR795 and refer the issue to ROS and WMS | Passed |
Background
Status: | Approved |
---|---|
Date Posted: | Nov 28, 2017 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 6.5.7.3 |
Description: | ERCOT is in the process of adding an intra-hour wind forecast. This System Change Request (SCR) updates the formula used by the Resource Limit Calculator to calculate the Generation To Be Dispatched (GTBD) value to include the addition of a predicted 5-minute wind ramp (PWRR). This PWRR will be calculated from the intra-hour wind forecast times five and a configurable factor to capture the forecasted 5-minute wind ramp. This addition would help Security-Constrained Economic Dispatch (SCED) take into account the potential 5-minute wind ramp in its 5-minute Base-Points and would take the burden off of Regulation to cover the 5-minute gain or loss of generation from variations in wind and instead dispatch this energy economically. This change will also aid reducing frequency recovery duration following events that occur during times with significant wind up and down ramps. Although there will be inherent forecast error in the intra-hour forecast, this change will give a better indication to SCED via GTBD of the level of wind generation that will be available in the next 5 minutes, as compared to the current assumption that the wind generation will persist at the same level as at the beginning of the 5-minute interval. Once ERCOT begins to receive the intra-hour wind forecast from its vendor(s), ERCOT will analyze the 5-minute out forecast performance and accuracy of projected wind generation ramp direction before the intra hour wind forecast component is activated in the GTBD formula. |
Reason: | Market efficiencies or enhancements |
Key Documents
Nov 28, 2017 - doc - 88 KB
Nov 28, 2017 - doc - 56.5 KB
Dec 15, 2017 - doc - 90.5 KB
Jan 11, 2018 - doc - 39 KB
Jan 12, 2018 - doc - 39 KB
Feb 5, 2018 - doc - 39 KB
Feb 13, 2018 - doc - 96 KB
Mar 12, 2018 - doc - 96 KB
Mar 23, 2018 - doc - 99 KB
Apr 11, 2018 - doc - 100 KB