Consensus to recommend approval of SMOGRR010 as submitted.
Passed
Background
Status:
Approved
Date Posted:
Jan 7, 2011
Sponsor:
ERCOT
Urgent:
No
Sections:
10.4.3
Description:
This Settlement Metering Operating Guide Revision Request (SMOGRR) reduces the comment period for SMOGRRs from 21 days to 14 days and removes the requirement for the comment period to end at least three Business Days prior to the next regularly scheduled Metering Working Group (MWG) meeting.
Reason:
As a result of the Technical Advisory Committee (TAC) structural and process review, TAC requested ERCOT staff to draft an NPRR to reduce the comment period for NPRRs to 14 days. Since SMOGRRs have a similar initial comment period, proposed revisions to the SMOG revision process are included in this SMOGRR to align with the Nodal Protocol revision process.