Summary

Title Modifications to Line Loss Compensation Requirement for EPS Metering
Next Group
Next Step
Status Approved on 05/12/2022
Effective Dates
06/01/2022

Action

Date Gov Body Action Taken Next Steps
05/12/2022 PUCT Approved
04/28/2022 BOARD Recommended for Approval Revision Request Consideration
04/13/2022 TAC Recommended for Approval Revision Request Consideration
04/06/2022 WMS Recommended for Approval Revision Request Consideration
03/02/2022 WMS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
05/12/2022 PUCT to approve SMOGRR025 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization Passed
04/28/2022 BOARD to recommend approval of SMOGRR025 as recommended by TAC in the 4/13/22 TAC Report Passed
04/13/2022 TAC to recommend approval of SMOGRR025 as recommended by WMS in the 4/6/22 WMS Report Passed
04/06/2022 WMS to endorse and forward to TAC the 3/2/22 WMS Report and Impact Analysis for SMOGRR025 Passed
03/02/2022 WMS to recommend approval of SMOGRR025 as submitted Passed

Background

Status: Approved
Date Posted: Jan 21, 2022
Sponsor: ERCOT
Urgent: No
Sections: 8.4
Description: This Settlement Metering Operating Guide Revision Request (SMOGRR) allows for losses in short runs of connecting lines to be disregarded in instances where the ERCOT-Polled Settlement (EPS) Meter is not physically placed at the Point of Interconnection (POI). This SMOGRR requires calculation to verify that the watts copper losses are below 0.001%.
Reason: Addresses current operational issues; Market efficiencies or enhancements