TX SET approved issue as a future implementation/clean-up effort for the 650_02 Implementation Guide Example 15--- Change control needs to be written for this issue or one clean-up change control for all example/graybox issues.
TX SET approved issue as a future implementation/clean-up effort for the 650_02 Implementation Guide Example 15--- Change control needs to be written for this issue or one clean-up change control for all example/graybox issues.
Background
Status:
Closed
Date Posted:
04/25/2007
Sponsor:
CenterPoint Energy
Urgent:
No
Sections:
650_02
Description:
Correct 650_02 Example 15 in Implementation Guide to include meter number based on graybox requirement in Guide
Reason:
Correction needed to ensure market is provided appropriate response transaction data segments/elements.