Summary

Title: Update the Implementation Guide for the 867_03 and 867_02 to show that the REF~JH~I will be used for kWh Generation values only and to state that if there are multiple REF~JH~I loops in the 867_03, that ERCOT will only read and use the first one in the transaction that is encountered.
Next Step: Updated to include kVA.
Status: Implemented

Action

Date Gov Body Action Taken Next Steps
02/22/2010 TXSET Approved Updated to include kVA.

Background

Status: Implemented
Date Submitted: 09/30/2008
Submitter Name: Kathryn Thurman
Submitter Company: ERCOT
Emergency: No
Sections: 867_03, 867_02
Description: Update the Implementation Guide for the 867_03 and 867_02 to show that the REF~JH~I will be used for kWh Generation values only and to state that if there are multiple REF~JH~I loops in the 867_03, that ERCOT will only read and use the first one in the transaction that is encountered.
Reason:
Version: 3.0A
Protocol Impact: No

Key Documents