Title: Revised PUCT Subs. rule 25.181 allows for the breakout of the Energy Efficiency Cost Recovery Factor (EECRF) from TDSPs base rates.
Next Step: Tabled until implementation of 3.0A.
Status: Implemented

Action

Date Gov Body Action Taken Next Steps
10/12/2010 TXSET Deferred/Tabled Tabled until implementation of 3.0A.
01/19/2011 RMS Approved Classified as Emergency by RMS. RMS approved on 1/19/2011 as future Implementation effective 02/21/2011
12/06/2010 TXSET Recommended for Approval TX SET Recommends for Approval as Emergency.
12/08/2010 RMS Approved Approved by RMS.

Background

Status: Implemented
Date Submitted: 10/22/2008
Submitter Name: Kathy Scott
Submitter Company: CenterPoint Energy
Emergency: Yes
Sections: 810_02
Description: Revised PUCT Subs. rule 25.181 allows for the breakout of the Energy Efficiency Cost Recovery Factor (EECRF) from TDSPs base rates.
Reason:
Version: 3.0A
Protocol Impact: No