| Title: | Create a new code in both the 650_01 and 650_02 transactions that will allow a CR to notify a TDSP when a customer has installed some type of generation equipment at the premise |
|---|---|
| Next Step: | |
| Status: | Implemented |
Action
| Date | Gov Body | Action Taken | Next Steps |
|---|---|---|---|
| 10/12/2010 | TXSET | Recommended for Approval | |
| 12/08/2010 | RMS | Approved | Approved by RMS |
| 01/19/2011 | RMS | Approved | Classified as Non-Emergency by RMS |
Background
| Status: | Implemented |
|---|---|
| Date Submitted: | 10/04/2010 |
| Submitter Name: | Kathy Scott |
| Submitter Company: | CenterPoint Energy |
| Emergency: | No |
| Sections: | 650_01 and 650_02 |
| Description: | Create a new code in both the 650_01 and 650_02 transactions that will allow a CR to notify a TDSP when a customer has installed some type of generation equipment at the premise |
| Reason: | This type of notification would also assist TDSPs so they can be aware of potential safety issues that could be present due to generating equipment or devices at a premise that may re-energize the distribution network during a power outage. |
| Version: | 4.0 |
| Protocol Impact: | No |