Title: Create a new code in both the 650_01 and 650_02 transactions that will allow a CR to notify a TDSP when a customer has installed some type of generation equipment at the premise
Next Step:
Status: Implemented

Action

Date Gov Body Action Taken Next Steps
10/12/2010 TXSET Recommended for Approval
12/08/2010 RMS Approved Approved by RMS
01/19/2011 RMS Approved Classified as Non-Emergency by RMS

Background

Status: Implemented
Date Submitted: 10/04/2010
Submitter Name: Kathy Scott
Submitter Company: CenterPoint Energy
Emergency: No
Sections: 650_01 and 650_02
Description: Create a new code in both the 650_01 and 650_02 transactions that will allow a CR to notify a TDSP when a customer has installed some type of generation equipment at the premise
Reason: This type of notification would also assist TDSPs so they can be aware of potential safety issues that could be present due to generating equipment or devices at a premise that may re-energize the distribution network during a power outage.
Version: 4.0
Protocol Impact: No