MIS LOG IN

TXSETCC759

Summary

Title: Add a new REF segment to the 814_16, 814_24 and 814_03 to provide key information to the TDSP about a condition that may affect the execution of a MVI, MVO or MVO to CSA
Next Step: It was determined the TDSP's can support this Change Control
Status: Implemented

Action

Date Gov Body Action Taken Next Steps
10/28/2010 TXSET Recommended for Approval It was determined the TDSP's can support this Change Control
01/19/2011 RMS Approved Classified as Non-Emergency by RMS
12/08/2010 RMS Approved Approved by RMS
10/21/2010 TXSET Under Review TDSP's must determine if they can support this Change Control

Background

Status: Implemented
Date Submitted: 10/20/2010
Submitter Name: Johnny Robertson
Submitter Company: TXU Energy
Emergency: No
Sections: 814_16, 814_24 & 814_03
Description: Add a new REF segment to the 814_16, 814_24 and 814_03 to provide key information to the TDSP about a condition that may affect the execution of a MVI, MVO or MVO to CSA.
Reason: Ability to provide key information to TDSP about condition that may affect execution of a MVI. Here are some examples of information: · Combination to gate · Which gate is unlocked · Time that the property is accessible · Instructions of where the meter is located · Time of day that is best to do the MVI or MVO · Location of the key for the gate
Version: 4.0
Protocol Impact: No

Key Documents

Related Content