Title: | This change control clarifies that several segments will not be provided in the 810_02 for the new "A5" Meter Tampering Charge invoice that was approved in 2010-755. |
---|---|
Next Step: | Approved as Non-Emergency by RMS on 10/19/11 |
Status: | Implemented |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
10/19/2011 | RMS | Approved | Approved as Non-Emergency by RMS on 10/19/11 |
10/13/2011 | MCT | Recommended for Approval | Recommended for Approval as Non-Emergency on 10/13/11. |
Background
Status: | Implemented |
---|---|
Date Submitted: | 10/06/2011 |
Submitter Name: | Kathy Scott |
Submitter Company: | CenterPoint Energy |
Emergency: | No |
Sections: | 810_02 |
Description: | This Change Control clarifies that several segments will not be provided in the 810_02 for the new "A5" Meter Tampering Charge invoice that was approved in 2010-755. This will correct the new "A5" Meter Tampering Charge to be similar to the Late Charge Invoice process. |
Reason: | |
Version: | 4.0 |
Protocol Impact: | No |