Title: Muni-Coop guidelines are different than the IOU guidelines for meter removal
Next Step: RMS Approved to withdraw this change control
Status: Withdrawn on 07/14/2020

Action

Date Gov Body Action Taken Next Steps
07/14/2020 RMS Withdrawn RMS Approved to withdraw this change control
06/17/2020 TXSET TX SET recommends that RMS withdraw Change Control 2013-800 as this language was incorporated into Change Control 2020-810
04/01/2014 RMS Approved Approved for Next Texas SET Version on 04/01/2014
03/19/2014 TXSET Recommended for Approval TX SET Recommends Change Control 800 for Approval as Non-Emergency
09/12/2013 TXSET Deferred/Tabled No representation from submitter of the Change Control on the Change Control call. TX SET has tabled discussion until next month.

Background

Status: Withdrawn
Date Submitted: 08/22/2013
Submitter Name: Paula Shadle
Submitter Company: Nueces Electric Coop
Emergency: No
Sections: 650_04
Description: When the Muni-Coop issues a 650_04 they pull the meter for a non-pay disconnect. The Muni-Coop will use the S2 action code in the BGN08. The CR's are wanting the Muni-Coop to use the R8 action code so that the CRs system will automatically trigger an 814_24. The Muni-Coop is disconnecting for non-pay and not because the customer called for disconnect, in which case the R8 action code is used. The Muni-Coop would like the CR's to understand that the guidelines are different for Muni-Coops than the IOU guidelines. Recommend adding the following to the S2 gray box "Required for MOU/EC: In order to avoid ongoing liability, a CR must submit an 814_24 to terminate service no earlier than five days after receipt of a 650_04 indicating successful completion of the disconnect for non-payment request." To clarify the use of S2 action code in MOU-EC market.
Reason: