- Home
- Market Rules
- Issues
TXSETCC802
Summary
Title: | Add a new SAC04 code of "PCR001" for Power Cost Recovery Factor |
---|---|
Next Step: | Approved as Emergency by RMS on 09/18/2013 |
Status: | Implemented |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
09/18/2013 | RMS | Approved | Approved as Emergency by RMS on 09/18/2013 |
09/12/2013 | TXSET | Recommended for Approval | Recommended for Approval as Emergency to RMS |
Background
Status: | Implemented |
---|---|
Date Submitted: | 09/04/2013 |
Submitter Name: | Kathy Scott |
Submitter Company: | CenterPoint Energy |
Emergency: | Yes |
Sections: | 810_02 and 810_03 |
Description: | During the July 17, 2013 STTF reviewed updates to the FAQs document that were drafted by Sharyland Utilities during that discussion the STTF identified a need for a new SAC04 Code that will need to be added to the 810_02 and 810_03 TX SET transactions to uniquely identify the Power Cost Recovery Factor. |
Reason: | The new Power Cost Recovery Factor SAC04 code of "PCR001" will be available to SU to support their transition to competition efforts found under the Final Order of PUCT Docket 39592: |
Version: | Future |
Protocol Impact: | No |
Key Documents
Sep 4, 2013 - doc - 227.5 KB
Sep 12, 2013 - doc - 392 KB
Sep 18, 2013 - doc - 384 KB