MIS LOG IN

VCMRR032

Summary

Title Calculation of Average Running Hours per Start when Determining the Variable O&M for QSGRs
Next Group
Next Step
Status Approved on 02/10/2022
Effective Dates
03/01/2022

Action

Date Gov Body Action Taken Next Steps
02/10/2022 PUCT Approved
01/31/2022 TAC Recommended for Approval Revision Request Consideration
12/01/2021 WMS Recommended for Approval Revision Request Consideration
11/03/2021 WMS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
02/10/2022 PUCT to approve VCMRR032 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization. Passed
01/31/2022 TAC to endorse and forward to TAC the 11/3/21 WMS Report and Impact Analysis for VCMRR032 Passed
12/01/2021 WMS to endorse and forward to TAC the 11/3/21 WMS Report and Impact Analysis for VCMRR032 Passed
11/03/2021 WMS to recommend approval of VCMRR032 as submitted Passed

Background

Status: Approved
Date Posted: Oct 19, 2021
Sponsor: ERCOT
Urgent: No
Sections: Appendix 7
Description: This Verifiable Cost Manual Revision Request (VCMRR) clarifies that the average run time per start is calculated by dividing the total running hours by the total number of starts during the 20 consecutive day period, and ensures that at a minimum, one start will be used in the calculation of the average run time per start when the Resource is operating on the first interval of the first day of the 20 consecutive day period.
Reason: Addresses current operational issues; Market efficiencies or enhancements

Key Documents