Summary

Title Related to NPRR1157, Incorporation of PUCT Approval into Revision Request Process
Next Group
Next Step
Status Approved on 05/11/2023
Effective Dates
06/01/2023

Action

Date Gov Body Action Taken Next Steps
05/11/2023 PUCT Approved
04/18/2023 BOARD Recommended for Approval Revision Request Process
03/21/2023 TAC Recommended for Approval Revision Request Consideration
03/01/2023 WMS Recommended for Approval Revision Request Consideration

Voting Record

Date Gov Body Motion Result
05/11/2023 PUCT to approve VCMRR036 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization Passed
04/18/2023 BOARD to recommend approval of VCMRR036 as recommended by TAC in the 3/21/23 TAC Report Passed
03/21/2023 TAC to recommend approval of VCMRR036 as recommended by WMS in the 3/1/23 WMS Report Passed
03/01/2023 WMS to grant VCMRR036 Urgent status; to recommend approval of VCMRR036 as revised by WMS; and to forward to TAC VCMRR036 and the 2/22/23 Impact Analysis Passed

Background

Status: Approved
Date Posted: Feb 22, 2023
Sponsor: ERCOT
Urgent: Yes
Sections: 13.1, 13.3.2, 13.3.3, 13.3.9, 13.3.10, 13.3.11 (new), 13.4, and 13.6
Description: This Verifiable Cost Manual Revision Request (VCMRR) requires all Revision Requests to be approved by the Public Utility Commission of Texas (PUCT) prior to implementation; standardizes all Revision Requests be considered by the ERCOT Board of Directors; adds an Independent Market Monitor (IMM) opinion, ERCOT opinion, and the ERCOT Market Impact Statement to the TAC Report; and revises possible actions on a Revision Request from “defer” to “table” as currently captured in motions.
Reason: Administrative; Regulatory requirements