MIS LOG IN

Southern Cross Transmission - Directive 6

Title: Determination regarding any needed transmission upgrades
Status: Complete
Description: As ordered by the Public Utility Commission of Texas (PUCT) in Project No. 46304: ERCOT shall study and determine what transmission upgrades, if any, are necessary to manage congestion resulting from power flows over the Southern Cross DC tie, make any necessary revisions to its standards, guides, systems, and protocols as appropriate, and certify to the Commission when it has completed these actions.