MIS LOG IN

Public Notices

This section contains public market notifications required by protocols as well as other market messages ERCOT may post for market transparency. ERCOT began archiving public notices November 3, 2011.

Jun 2024 Jul 2024 Aug 2024 Sep 2024 Oct 2024 Nov 2024
Date & Time Notice Type Status
Sep 30, 2024 11:12:30 AM ERCOT has cancelled the following notice: The DC_E (East) DC Tie will be unavailable from 09/30/2024 09:44 through 09/30/2024 23:59 due to a forced outage. Operational Information Cancelled
Sep 30, 2024 9:56:46 AM The DC_E (East) DC Tie will be unavailable from 09/30/2024 09:44 through 09/30/2024 23:59 due to a forced outage. Operational Information Active
Sep 30, 2024 9:05:09 AM The Daily RSASM for 09/30/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 30, 2024 12:13:51 AM No sudden loss of generation greater than 450 MW occurred on September 29, 2024. Operational Information Active
Sep 29, 2024 8:21:11 PM At 20:20, All Non-Spin has been recalled. Operational Information Active
Sep 29, 2024 8:20:25 PM CM-ASM-NOTF AS_TYPE: Non-Spin, DEPLOY_MW: 0.0, BEGIN_TIME: 2024-09-29 20:20:25, END_TIME: 2024-09-29 20:20:25, DURATION: 0 Hrs 0 Mins.; Operational Information
Sep 29, 2024 8:09:50 PM At 20:06, 519 Non-Spin has been recalled. Operational Information Active
Sep 29, 2024 8:06:14 PM CM-ASM-NOTF AS_TYPE: Non-Spin, DEPLOY_MW: 634.2, BEGIN_TIME: 2024-09-29 20:06:14, END_TIME: 2024-09-29 23:59:00, DURATION: 3 Hrs 52 Mins.; Operational Information
Sep 29, 2024 7:33:01 PM CM-ASM-NOTF AS_TYPE: Non-Spin, DEPLOY_MW: 1159.0, BEGIN_TIME: 2024-09-29 20:00:00, END_TIME: 2024-09-29 23:59:00, DURATION: 3 Hrs 59 Mins.; Operational Information
Sep 29, 2024 6:49:55 PM Correction to previous notice: At 18:33 approximately 1148 MW of Non-Spin has been deployed, anticipated duration is 23:59. Operational Information Active
Sep 29, 2024 6:37:35 PM At 18:33 approximately 1340 MW of Non-Spin has been deployed, anticipated duration is 29:59. Operational Information Active
Sep 29, 2024 6:33:01 PM CM-ASM-NOTF AS_TYPE: Non-Spin, DEPLOY_MW: 1148.7, BEGIN_TIME: 2024-09-29 19:00:00, END_TIME: 2024-09-29 23:59:00, DURATION: 4 Hrs 59 Mins.; Operational Information
Sep 29, 2024 6:28:40 PM CM-ASM-NOTF AS_TYPE: Non-Spin, DEPLOY_MW: 790.4, BEGIN_TIME: 2024-09-29 18:28:40, END_TIME: 2024-09-29 23:59:00, DURATION: 5 Hrs 30 Mins.; Operational Information
Sep 29, 2024 6:27:28 PM At 18:25 approximately 790 MW of Non-Spin has been deployed, anticipated duration is until 23:59. Operational Information Active
Sep 29, 2024 8:46:27 AM The Daily RSASM for 09/29/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 29, 2024 12:09:17 AM No sudden loss of generation greater than 450 MW occurred on September 28, 2024. Operational Information Active
Sep 28, 2024 8:46:22 AM The Daily RSASM for 09/28/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 28, 2024 12:55:37 AM No sudden loss of generation greater than 450 MW occurred on September 27, 2024. Operational Information Active
Sep 27, 2024 9:48:45 AM ERCOT has cancelled the following notice: The DC_E (East) DC Tie will be unavailable from 09/16/2024 07:00 through 09/27/2024 17:00 due to a planned outage. Operational Information Cancelled
Sep 27, 2024 8:46:54 AM The Daily RSASM for 09/27/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 27, 2024 12:00:24 AM No sudden loss of generation greater than 450 MW occurred on September 26, 2024. Operational Information Active
Sep 26, 2024 8:47:21 AM The Daily RSASM for 09/26/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 26, 2024 12:00:34 AM No sudden loss of generation greater than 450 MW occurred on September 25, 2024. Operational Information Active
Sep 25, 2024 4:53:12 PM The DC_E (East) DC Tie will be unavailable from 09/16/2024 07:00 through 09/27/2024 17:00 due to a planned outage. Operational Information Active
Sep 25, 2024 4:52:00 PM ERCOT has cancelled the following notice: The DC_E (East) DC Tie will be unavailable from 09/16/2024 07:00 through 09/25/2024 17:00 due to a planned outage. Operational Information Cancelled
Sep 25, 2024 8:47:47 AM The Daily RSASM for 09/25/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 25, 2024 12:04:47 AM No sudden loss of generation greater than 450 MW occurred on September 24, 2024. Operational Information Active
Sep 24, 2024 8:48:01 AM The Daily RSASM for 09/24/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 24, 2024 12:02:36 AM On September 23, 2024, a sudden loss of generation occurred at 16:12 totaling 498 MW. Frequency declined to 59.943 Hz, ERCOT load was 68,583 MW. Operational Information Active
Sep 23, 2024 11:43:00 AM ERCOT has cancelled the following notice: ERCOT has been notified that the Railroad DC Tie has been derated to 150 MW Import/Export due to equipment issues until further notice. Operational Information Cancelled
Sep 23, 2024 10:06:21 AM ERCOT has been notified that the Railroad DC Tie has been derated to 150 MW Import/Export due to equipment issues until further notice. Operational Information Active
Sep 23, 2024 8:52:28 AM The Daily RSASM for 09/23/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 23, 2024 12:04:23 AM No sudden loss of generation greater than 450 MW occurred on September 22, 2024. Operational Information Active
Sep 22, 2024 9:03:13 PM ERCOT has cancelled the following notice: The DC_N (North) DC Tie will be unavailable from 09/22/2024 17:30 through 09/23/2024 01:00 due to a forced outage. Operational Information Cancelled
Sep 22, 2024 5:45:38 PM The DC_N (North) DC Tie will be unavailable from 09/22/2024 17:30 through 09/23/2024 01:00 due to a forced outage. Operational Information Active
Sep 22, 2024 5:16:08 PM ERCOT has cancelled the following notice: 13:06 ERCOT has been notified that the RAILROAD DC Tie has been derated to 150MW Import/Export due to equipment issues until further notice. Operational Information Cancelled
Sep 22, 2024 1:19:34 PM 13:06 ERCOT has been notified that the RAILROAD DC Tie has been derated to 150MW Import/Export due to equipment issues until further notice. Operational Information Active
Sep 22, 2024 8:47:05 AM The Daily RSASM for 09/22/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 22, 2024 12:09:33 AM No sudden loss of generation greater than 450 MW occurred on September 21, 2024. Operational Information Active
Sep 21, 2024 8:47:18 AM The Daily RSASM for 09/21/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 21, 2024 12:21:05 AM No sudden loss of generation greater than 450 MW occurred on September 20, 2024. Operational Information Active
Sep 20, 2024 8:46:36 AM The Daily RSASM for 09/20/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 20, 2024 12:05:25 AM No sudden loss of generation greater than 450 MW occurred on September 19, 2024. Operational Information Active
Sep 19, 2024 8:46:58 AM The Daily RSASM for 09/19/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 19, 2024 12:16:34 AM No sudden loss of generation greater than 450 MW occurred on September 18, 2024. Operational Information Active
Sep 18, 2024 8:47:38 AM The Daily RSASM for 09/18/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 18, 2024 12:18:38 AM No sudden loss of generation greater than 450 MW occurred on September 17, 2024. Operational Information Active
Sep 18, 2024 12:18:05 AM No sudden loss of generation greater than 450 MW occurred on September 16, 2024. Operational Information Active
Sep 17, 2024 8:47:59 AM The Daily RSASM for 09/17/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 17, 2024 7:02:29 AM ERCOT has cancelled the following notice: Advisory issued for a geomagnetic disturbance of K-8 until 0700 CT on 9/17/24. Advisory Cancelled
Sep 16, 2024 10:19:05 PM ERCOT has cancelled the following notice: Advisory issued for a geomagnetic disturbance of K-7 until 0700 CT on 9/17/24. Advisory Cancelled
Sep 16, 2024 10:18:49 PM Advisory issued for a geomagnetic disturbance of K-8 until 0700 CT on 9/17/24. Advisory Active
Sep 16, 2024 9:42:22 PM ERCOT has cancelled the following notice: Advisory issued for a geomagnetic disturbance of K-7 until 0700 CST on 9/16/24. Advisory Cancelled
Sep 16, 2024 9:42:13 PM Advisory issued for a geomagnetic disturbance of K-7 until 0700 CT on 9/17/24. Advisory Active
Sep 16, 2024 8:44:52 PM Advisory issued for a geomagnetic disturbance of K-7 until 0700 CST on 9/16/24. Advisory Active
Sep 16, 2024 8:47:41 AM The Daily RSASM for 09/16/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 16, 2024 12:06:06 AM The minimum monthly Ancillary Services quantities have been posted to the ERCOT Website; Data Products; Grid; Forecasts under the Projected Ancillary Service Requirements link located under the Reports & Extracts heading. The posted quantities reflect minimum requirements only. ERCOT will follow-up with a Notification if any upward adjustments to these minimum quantities are made. https://mis.ercot.com/secure/data-products/grid/forecasts AS Postings Active
Sep 16, 2024 12:04:24 AM No sudden loss of generation greater than 450 MW occurred on September 15, 2024. Operational Information Active
Sep 15, 2024 8:46:15 AM The Daily RSASM for 09/15/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 15, 2024 7:24:55 AM The DC_E (East) DC Tie will be unavailable from 09/16/2024 07:00 through 09/25/2024 17:00 due to a planned outage. Operational Information Active
Sep 15, 2024 12:08:43 AM No sudden loss of generation greater than 450 MW occurred on September 14, 2024. Operational Information Active
Sep 14, 2024 8:45:55 AM The Daily RSASM for 09/14/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 14, 2024 12:02:59 AM No sudden loss of generation greater than 450 MW occurred on September 13, 2024. Operational Information Active
Sep 13, 2024 1:41:28 PM ERCOT has cancelled the following notice: The DC_L (Laredo VFT) DC Tie will be unavailable from 09/09/2024 07:00 through 09/13/2024 17:00 due to a planned outage. Operational Information Cancelled
Sep 13, 2024 8:45:46 AM The Daily RSASM for 09/13/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 13, 2024 12:06:04 AM No sudden loss of generation greater than 450 MW occurred on September 12, 2024. Operational Information Active
Sep 12, 2024 4:15:15 PM ERCOT has cancelled the following notice: The Space Weather Prediction Center has issued a GMD Warning of K-7 or greater until September 12, 2024, 1600. Operational Information Cancelled
Sep 12, 2024 4:15:06 PM ERCOT has cancelled the following notice: Advisory issued for a geomagnetic disturbance of K-7 until September 12, 2024. 1600. Advisory Cancelled
Sep 12, 2024 10:03:10 AM Advisory issued for a geomagnetic disturbance of K-7 until September 12, 2024. 1600. Advisory Active
Sep 12, 2024 9:36:00 AM At 3:25 PM on 09/12/2024, ERCOT will perform site failover of its Energy & Market Management Systems. During this time, market communications will be unavailable for about 20 minutes, and real-time communications will be unavailable for about 5 minutes. All systems should re-establish communications automatically. This event will be preceded by a "hot line" call shortly before beginning. Operational Information Active
Sep 12, 2024 8:46:02 AM The Daily RSASM for 09/12/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 12, 2024 8:44:58 AM The Space Weather Prediction Center has issued a GMD Warning of K-7 or greater until September 12, 2024, 1600. Operational Information Active
Sep 12, 2024 12:06:13 AM No sudden loss of generation greater than 450 MW occurred on September 11, 2024. Operational Information Active
Sep 11, 2024 5:00:33 PM ERCOT has cancelled the following notice: At 11:00, ERCOT is issuing an Advisory for Tropical Storm Francine in the Gulf of Mexico which has a potential impact to the ERCOT Region from Monday, September 9, 2024, through Wednesday, September 11, 2024. Advisory Cancelled
Sep 11, 2024 5:00:19 PM ERCOT has cancelled the following notice: At 20:30, ERCOT is issuing an OCN for Potential Tropical Cyclone Six expected to increase into Tropical Storm Francine and potentially impact or making landfall in the ERCOT Region as early as Monday, September 9, 2024. Operational Information Cancelled
Sep 11, 2024 8:46:52 AM The Daily RSASM for 09/11/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 11, 2024 12:09:13 AM No sudden loss of generation greater than 450 MW occurred on September 10, 2024. Operational Information Active
Sep 10, 2024 11:00:01 AM ERCOT has cancelled the following notice: The DC_E (East) DC Tie is being curtailed, a DC Tie Curtailment Notice (DCTCN) is active due to one or more transmission security violations that would be fully or partially resolved by the curtailment of DC Tie Load. DC Tie Curtailment Notice Cancelled
Sep 10, 2024 10:16:27 AM The DC_E (East) DC Tie is being curtailed, a DC Tie Curtailment Notice (DCTCN) is active due to one or more transmission security violations that would be fully or partially resolved by the curtailment of DC Tie Load. DC Tie Curtailment Notice Active
Sep 10, 2024 8:46:41 AM The Daily RSASM for 09/10/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 10, 2024 12:06:49 AM No sudden loss of generation greater than 450 MW occurred on September 9, 2024. Operational Information Active
Sep 9, 2024 2:25:35 PM Notification of Prices Under Investigation. ERCOT has discovered a potential issue with values being used in the Energy Management System (EMS) that may have impacted Real-Time Market Prices on Operating Date (OD) 09/05/2024 interval 08:35. ERCOT is investigating the potential impact to Real-Time Market prices for this event as well as previous operating days. A follow-up Market Notice will be issued once ERCOT has more information. If a price correction is needed for OD 09/05/2024, the posting deadline is 16:00 on 09/09/2024. Alert Active
Sep 9, 2024 11:00:01 AM At 11:00, ERCOT is issuing an Advisory for Tropical Storm Francine in the Gulf of Mexico which has a potential impact to the ERCOT Region from Monday, September 9, 2024, through Wednesday, September 11, 2024. Advisory Active
Sep 9, 2024 8:46:33 AM The Daily RSASM for 09/09/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 9, 2024 12:00:29 AM No sudden loss of generation greater than 450 MW occurred on September 8, 2024. Operational Information Active
Sep 8, 2024 8:31:54 PM At 20:30, ERCOT is issuing an OCN for Potential Tropical Cyclone Six expected to increase into Tropical Storm Francine and potentially impact or making landfall in the ERCOT Region as early as Monday, September 9, 2024. Operational Information Active
Sep 8, 2024 8:46:33 AM The Daily RSASM for 09/08/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 8, 2024 12:01:14 AM No sudden loss of generation greater than 450 MW occurred on September 7, 2024. Operational Information Active
Sep 7, 2024 11:55:22 AM ERCOT has cancelled the following notice: ERCOT will execute a SASM at [1145] for operating day 09/07/2024 for 3MW RRS for HE 14-24. Operational Information Cancelled
Sep 7, 2024 11:06:12 AM ERCOT will execute a SASM at [1145] for operating day 09/07/2024 for 3MW RRS for HE 14-24. Operational Information Active
Sep 7, 2024 8:46:38 AM The Daily RSASM for 09/07/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 7, 2024 7:11:51 AM The DC_L (Laredo VFT) DC Tie will be unavailable from 09/09/2024 07:00 through 09/13/2024 17:00 due to a planned outage. Operational Information Active
Sep 7, 2024 12:01:02 AM No sudden loss of generation greater than 450 MW occurred on September 6, 2024. Operational Information Active
Sep 6, 2024 5:27:44 PM ERCOT has cancelled the following notice: The DC_N (North) DC Tie will be unavailable from 09/03/2024 08:00 through 09/07/2024 17:00 due to a planned outage. Operational Information Cancelled
Sep 6, 2024 2:02:54 PM ERCOT has cancelled the following notice: ERCOT will execute a SASM at [1350] for operating day 09/06/2024 for 25MW RRS for HE 16-18, 15.2MW RRS for HE 19, 24.8MW RRS for HE20, 22.9MW RRS for HE21-22, 24.6MW RRS for HE23, and 24.4MW RRS for HE24 Operational Information Cancelled
Sep 6, 2024 1:17:44 PM ERCOT will execute a SASM at [1350] for operating day 09/06/2024 for 25MW RRS for HE 16-18, 15.2MW RRS for HE 19, 24.8MW RRS for HE20, 22.9MW RRS for HE21-22, 24.6MW RRS for HE23, and 24.4MW RRS for HE24 Operational Information Active
Sep 6, 2024 8:45:53 AM The Daily RSASM for 09/06/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 6, 2024 3:59:49 AM ERCOT will be working from the primary control center until further notice, use the OPX numbers for Taylor. Operational Information Active
Sep 6, 2024 3:59:27 AM ERCOT has cancelled the following notice: ERCOT will be working from the alternate control center until further notice, use the OPX numbers for Bastrop. Operational Information Cancelled
Sep 6, 2024 12:05:21 AM No sudden loss of generation greater than 450 MW occurred on September 5, 2024. Operational Information Active
Sep 5, 2024 3:58:14 PM ERCOT will be working from the alternate control center until further notice, use the OPX numbers for Bastrop. Operational Information Active
Sep 5, 2024 8:45:41 AM The Daily RSASM for 09/05/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 5, 2024 3:04:29 AM ERCOT has cancelled the following notice: ERCOT will execute a SASM at 02:50 for operating day 09/05/2024 for 3.5 MW ECRS HE 8-15 and 3.7 MW ECRS HE 16-24. Operational Information Cancelled
Sep 5, 2024 2:14:02 AM ERCOT will execute a SASM at 02:50 for operating day 09/05/2024 for 3.5 MW ECRS HE 8-15 and 3.7 MW ECRS HE 16-24. Operational Information Active
Sep 5, 2024 12:07:10 AM No sudden loss of generation greater than 450 MW occurred on September 4, 2024. Operational Information Active
Sep 4, 2024 7:18:36 PM ERCOT has cancelled the following notice: ERCOT is taking manual action for a BASECASE contingency in the southern ERCOT region. Operational Information Cancelled
Sep 4, 2024 3:35:03 PM ERCOT is taking manual action for a BASECASE contingency in the southern ERCOT region. Operational Information Active
Sep 4, 2024 8:45:09 AM The Daily RSASM for 09/04/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 4, 2024 12:05:29 AM No sudden loss of generation greater than 450 MW occurred on September 3, 2024. Operational Information Active
Sep 3, 2024 5:14:44 PM ERCOT has cancelled the following notice: ERCOT will execute a SASM at 16:50 for operating day 09/03/2024 for 96 MW ECRS HE 20-23, 44.7 MW ECRS HE 24, 30 MW RegDN HE 20, 20 MW RegDN HE 21-22, 42 MW RRS HE 22, and 64 MW RRS HE 23-24. Operational Information Cancelled
Sep 3, 2024 4:14:20 PM ERCOT will execute a SASM at 16:50 for operating day 09/03/2024 for 96 MW ECRS HE 20-23, 44.7 MW ECRS HE 24, 30 MW RegDN HE 20, 20 MW RegDN HE 21-22, 42 MW RRS HE 22, and 64 MW RRS HE 23-24. Operational Information Active
Sep 3, 2024 3:16:07 PM ERCOT has cancelled the following notice: ERCOT will execute a SASM at 14:45 for operating day 09/03/24 this is for ECRS HE17 to HE18 89.4 MWs each hour and for RRS 10.6 MWs each hour. Also REGDOWN HE17 64.3 MWs. Operational Information Cancelled
Sep 3, 2024 2:18:14 PM ERCOT will execute a SASM at 14:45 for operating day 09/03/24 this is for ECRS HE17 to HE18 89.4 MWs each hour and for RRS 10.6 MWs each hour. Also REGDOWN HE17 64.3 MWs. Operational Information Active
Sep 3, 2024 10:09:00 AM ERCOT has cancelled the following notice: ERCOT will execute a SASM at 9:45 for operating day 09/03/24 this is for ECRS HE12 to HE17 96 MWs each hour and for RRS HE12 10 MWS, HE13 10 MWs, HE14 4.2 MWs and for REGUP HE13 54 MWs, HE14 to HE16 24 MWs, HE17 40 MWs, HE19 54 MWs. Operational Information Cancelled
Sep 3, 2024 9:22:53 AM ERCOT will execute a SASM at 9:45 for operating day 09/03/24 this is for ECRS HE12 to HE17 96 MWs each hour and for RRS HE12 10 MWS, HE13 10 MWs, HE14 4.2 MWs and for REGUP HE13 54 MWs, HE14 to HE16 24 MWs, HE17 40 MWs, HE19 54 MWs. Operational Information Active
Sep 3, 2024 8:45:21 AM The Daily RSASM for 09/03/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 3, 2024 2:23:17 AM The DC_N (North) DC Tie will be unavailable from 09/03/2024 08:00 through 09/07/2024 17:00 due to a planned outage. Operational Information Active
Sep 3, 2024 12:06:45 AM No sudden loss of generation greater than 450 MW occurred on September 2, 2024. Operational Information Active
Sep 2, 2024 5:10:54 PM ERCOT has cancelled the following notice: ERCOT will execute a SASM at 16:50 for operating day 09/02/2024 for 96 MW ECRS HE 19-24, 38 MW RegDN HE 20, 50 MW RegDN HE 21, 60 MW RegDN HE 22, 54 MW RegUP HE 19, 26 MW RegUP HE 20, 26 MW RRS HE 21, 42 MW RRS HE 22, and 64 MW RRS HE 23-24. Operational Information Cancelled
Sep 2, 2024 4:14:52 PM ERCOT will execute a SASM at 16:50 for operating day 09/02/2024 for 96 MW ECRS HE 19-24, 38 MW RegDN HE 20, 50 MW RegDN HE 21, 60 MW RegDN HE 22, 54 MW RegUP HE 19, 26 MW RegUP HE 20, 26 MW RRS HE 21, 42 MW RRS HE 22, and 64 MW RRS HE 23-24. Operational Information Active
Sep 2, 2024 3:06:23 PM ERCOT has cancelled the following notice: ERCOT will execute a SASM at 14:45 for operating day 09/02/24 this is for RRS HE 17 and HE 18 13 MWs each hour. Operational Information Cancelled
Sep 2, 2024 2:26:19 PM ERCOT will execute a SASM at 14:45 for operating day 09/02/24 this is for RRS HE 17 and HE 18 13 MWs each hour. Operational Information Active
Sep 2, 2024 11:09:42 AM ERCOT has cancelled the following notice: ERCOT will execute a SASM at 10:45 for operating day 09/02/24 this is for HE 13 - ECRS 96 MWs, REGUP 54 MWs, RRS 10 MWs. HE 14 - ECRS 96 MWs, REGUP 24 MWs, RRS 40 MWs. HE 15 - ECRS 96 MWs, REGUP 16 MWs, REGDOWN 40 MWs. HE 16 – ECRS 96 MWs, REGUP 48 MWs. HE 17 – ECRS 96 MWs, REGUP 34 MWs, REGDOWN 16.8 MWs. Operational Information Cancelled
Sep 2, 2024 10:21:40 AM ERCOT will execute a SASM at 10:45 for operating day 09/02/24 this is for HE 13 - ECRS 96 MWs, REGUP 54 MWs, RRS 10 MWs. HE 14 - ECRS 96 MWs, REGUP 24 MWs, RRS 40 MWs. HE 15 - ECRS 96 MWs, REGUP 16 MWs, REGDOWN 40 MWs. HE 16 – ECRS 96 MWs, REGUP 48 MWs. HE 17 – ECRS 96 MWs, REGUP 34 MWs, REGDOWN 16.8 MWs. Operational Information Active
Sep 2, 2024 8:45:07 AM The Daily RSASM for 09/02/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 2, 2024 8:06:37 AM ERCOT has cancelled the following notice: ERCOT will execute a SASM at 07:45 for operating day 09/02/24 this is for RRS for HE10 and HE11- 64 MWs per hour and ECRS for HE11- 96 MWs. Operational Information Cancelled
Sep 2, 2024 7:20:09 AM ERCOT will execute a SASM at 07:45 for operating day 09/02/24 this is for RRS for HE10 and HE11- 64 MWs per hour and ECRS for HE11- 96 MWs. Operational Information Active
Sep 2, 2024 12:04:21 AM No sudden loss of generation greater than 450 MW occurred on September 1, 2024. Operational Information Active
Sep 1, 2024 11:08:12 AM ERCOT has cancelled the following notice: ERCOT will be performing a SASM at 0950 for ECRS 44 MW HE 12, 12.7 MW HE 15, 37.7 MW HE 16, 30 MW HE 17 – 18. For REGUP 30 MW HE 12, 9.8 MW HE 19. For RRS 16 MW HE 12, 7.3 MW HE 15. Operational Information Cancelled
Sep 1, 2024 9:12:42 AM ERCOT will be performing a SASM at 0950 for ECRS 44 MW HE 12, 12.7 MW HE 15, 37.7 MW HE 16, 30 MW HE 17 – 18. For REGUP 30 MW HE 12, 9.8 MW HE 19. For RRS 16 MW HE 12, 7.3 MW HE 15. Operational Information Active
Sep 1, 2024 8:53:55 AM The Daily RSASM for 09/01/2024 will not be occurring due to zero participating QSEs. Operational Information Active
Sep 1, 2024 12:05:38 AM No sudden loss of generation greater than 450 MW occurred on August 31, 2024. Operational Information Active