Agenda
1. |
Antitrust Admonition
|
S. Morris |
2. |
Approval of Minutes (Vote) July 23, 2009 |
S. Morris |
3. |
Urgency Votes (Possible Vote)
|
S. Morris |
4. |
TAC and Board Reports TAC Procedures - Notification (Possible Vote)
|
S. Morris S. Morris |
5. |
Project Update and Summary of Project Priority List (PPL) Activity to Date
|
T. Anderson |
6. |
Other Binding Documents Update
|
D. Seibert |
7. |
Review of Recommendation Report, Impact Analysis and Cost/Benefit Analysis (Vote) PRR811, Real Time Production Potential PRR817, Cease Late Payment Charges for Defaulted Entities NPRR165, Synchronizing Section 1 with PRR697 NPRR168, Verifiable Costs General Corrections NPRR183, Synchronization of PRR790, Load Profile ID Annual Validation Change Request NPRR184, Section 2, Addition of Definitions and Acronyms from Zonal Protocols and Clarifications NPRR185, Cancellations of RUC-Committed Resources NPRR186, Naming Convention Clarification NPRR188, MVA for SCED Input
|
S. Morris |
8. |
Review of Protocol Revision Requests (PRRs) Language (Vote) PRR818, OOMC for Quick Start Units - URGENT PRR821, Update of Section 21, Process for Protocol Revision PRR823, Clarifying Language for Resource 12-Month Rolling Planned Outage Schedule PRR824, Primary Frequency Response from WGRs PRR825, Distributed Energy Resource Participation in Responsive Reserve Service Markets PRR826, Clarification of Resource Definitions and Resource Registration of Self-Serve Generators for Reliability Purposes
|
S. Morris |
9. |
Review of Nodal Protocol Revision Requests (NPRRs) Language (Vote) NPRR189, Ancillary Service Deployment Clarification NPRR190, Clarification of Resource Definitions and Resource Registration of Self-Serve Generators for Reliability Purposes NPRR191, Synchronization of PRR819, Changes to Support Revisions to the PUCT POLR and Expedited Switch Rules NPRR192, QSE Energy and Ancillary Service Compliance Criteria NPRR193, Application of Nodal Implementation Surcharge in Verifiable Costs NPRR194, Synchronization of Zonal Unannounced Generation Capacity Testing Process NPRR195, Removal of McCamey Congestion Management from Nodal Protocols
|
S. Morris |
10. |
Notice of NPRRs with CEO Determination of "Not Needed for Go-Live"
|
S. Morris |
11. |
Notice of Withdrawal PRR813, FIP Definition Revision
|
S. Morris
|
12. |
Other Business
|
S. Morris |
13. |
Adjourn
|
S. Morris |
14. |
Future PRS Meetings
|
|
Scheduled PRS Meetings
- Aug 14, 2009 - Discussion of PRR818, OOMC for Quick Start Units
- Aug 20, 2009 - PRS Meeting (CANCELLED)
- Aug 25, 2009 - PRS Meeting
- Sep 02, 2009 - Other Binding Documents Meeting
- Sep 11, 2009 - Discussion of PRR826 and NPRR190
- Sep 17, 2009 - PRS Meeting
- Sep 22, 2009 - Special PRS Meeting